Nyrstar Hobart
2018 Turnaround Project
Nyrstar Hobart – 2018 Turnaround Project2019-04-09T14:51:18+00:00

Project Description

Repairs to Acid plant stripping tower, repacking of ceramics, installation of new distributors and desludging and cleaning of acid storage tank.

Some text below the image

Some text below the image

Reason for Engagement

High Impact Acid Solutions are a Acid plant maintenance company that specialise in this work.

Scope of Work

  • Specialised vessel entry using fully encapsulated suits
  • Acid sludge neutralisation and disposal
  • Specialised welding
  • Vessel inspection services
  • Ceramic packing unloading and loading

Services

  • Acid Plant Maintenance and Shutdowns
  • Internal Acid Vessel Inspection & Maintenance
  • Tank Desludging and Neutralisation
  • Specialised Welding and Mechanical Services
  • Ceramic and Terrapacking Loading and Unloading
  • Decontamination

Key Outcomes

Successfully completed project within scheduled time frame, Zero safety events, all work completed to meet quality standards.